JOB DESCRIPTION

Job Description (JD)

Nama ProgramPengurusan Pemeriksaan Letupan& Penyalutan [OG-023-4:2013]
Kod CUOG-023-4:2013-E04
CompetencyElektif
Tajuk CULining Coating Works Inspection
Penerangan CULine coating works inspection is the quality control process of ensuring that the line coating applied complies with international coating standards and client requirements. Lining coating is a coating system that uses fusion-bonded epoxy (FBE) and polypropylene to produce high performance corrosion protection for pipelines.

This CU covers the roles of the coating inspector in determining the readiness for commencement of lining coating operation as well as in verifying the compliance of the coating application and quality with the specified standards.

The person who is competent in this CU will be able to identify line coating works inspection requirements, check environmental condition, check line coating operator competencies certification, verify HSE compliance, determine status for commencement of line coating work activities, monitor line coating activities and conduct WFT and DFT inspection.

The outcome of this competency is to determine the readiness for line coating operation and to ensure compliance of line coating works with international blasting & coating standards and client requirements
Tempoh Latihan350
Objektif PembelajaranThe person who is competent in this CU shall be able to perform lining coating operation in accordance with blasting & coating standards and client requirements. Upon completion of this competency unit, trainees will be able to:-
• Ide
ntify lining coating job requirements
• Pr
epare lining coating work area
• P
repare lining coating tools and equipment

Carry out preliminary check on items to be coated
• P
repare lining coating materials
• Ch
eck climatic condition
•Per
form external surface preparation
• P
erform external coating
• Pe
rform internal surface preparation
• Per
form internal coating
• M
easure dry film thickness (DFT) of lining coating
• P
erform field-joint external coating after welding
• Pe
rform housekeeping activities
Pra-Syarat0